Project
Summary:
The Discover Mills
- Remodel & Parking Deck project comprises three parts:
1. Pad Preparation & Building Build-out
Approximate 8,000 SF of existing base building and 65,000 SF of existing
parking area, including underground utilities, will be demolished to
accommodate the new
AMC
Theatre. Approximate 9,200 CY fill material will be imported for theater
building pad. New construction consists of approximate 17,500 SF new steel
structure
and
interior / exterior walls at Base Building area (Shell Only).
2. Entry Road #3
Entry Road #3 will provide the access from Sugarloaf Parkway to the
Discover Mills Mall outer ring road. The work consists of grading and
infrastructure work (storm
sewer,
roads, traffic signal, etc.) for a new private road (500 LF) and associated
median work on Sugarloaf Parkway.
3. Parking Deck
The Parking Deck is a precast structure with one slab on grade and two
elevated decks. The total square footage of the deck is approximately
250,000 and 795 parking spaces will be provided. The works consists of site
demo, precast erection, and underground utility work. Beck will be
providing Design / Build services for the Parking Deck.
|