Virtual rendering of the new art museum. |
Virtual rendering of the new art museum. |
Mr. Nasher discusses the mock-up with the Architect and the
Museum Director. |
The whole group stands back to look at the precast mock-up. |
Reinforcing steel has been delivered to the jobsite. |
Pavilion III's building pad is a muddy mess with the
groundwater issue. |
Preparing Pavilion III's drainage system |
Rick Larosa facilitated our Project Expectations Conference in
the existing art museum. |
The Administration Building is laid out and ready to start
footings. |